TRANSPORTATION, DEPARTMENT OF · Medora, ND

ND NP THRO 204(1) Buck Hill Road

13 source documentsSource checked Oct 5Content updated
Open notice
Response deadline
11 days left
Published project value
$5.0M – $10M
As stated in the source documents
Solicitation number
ND NP THRO 204(1)
View official posting ↗Review requirements ↓Original posting details are available below.

Dates to plan around

Times follow the original source.

  1. Response deadline
    Source wording
    2026-11-03T14:00:00-07:00
From the posting4 agency details · contact information and original wording
Solicitation number
ND NP THRO 204(1)
Status
OPEN
Worth confirming on the posting
Estimated value
$5,000,000
Scope
Buck Hill Road, also known as Route 204, is located in Billings County within Theodore Roosevelt (THRO) National Park (NP) in the southeast portion of the park near the South Unit,
View the official posting →Always the authority. An addendum can change any of this after we read it.
Document coverage
9 / 13documents readReview incomplete

13 documents found1 need OCR3 could not be read24% of weighted requirement checks reviewed

Newer source changes have not been verified. Confirm the latest notice and addenda before submitting.

Before you bid

Review first

Start with these requirements and unresolved points.
01

Eligibility & participation

Whether you can bid at all, and what you must already hold.

21 verified12 to confirm

Registrations

4 findings
Requirement 1Verified

Notice of SAM Registration – Offerors or quoters are required to have an active Federal Government contracts registration in the System for Award Management (SAM) when they submit an offer or quotation, and at the time of award.

Applies when: when they submit an offer or quotation, and at the time of award; at the time of awardMust be met by: at the time of award

View source 1
01page 5View official source ↗
“Notice of SAM Registration – Offerors or quoters are required to have an active Federal Government contracts registration in the System for Award Management (SAM) when they submit an offer or quotation, and at the time of award.”
Source page 5

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 5
Requirement 2Verified
(Include area code) 16. REMITTANCE ADDRESS (Include only if different than Item 14) UEI. 17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writRead full requirement Close full requirement

(Include area code) 16. REMITTANCE ADDRESS (Include only if different than Item 14) UEI. 17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writ

Applies when: if different than Item 14) UEI

View source 1
01page 10View official source ↗
“(Include area code) 16. REMITTANCE ADDRESS (Include only if different than Item 14) UEI. 17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing with 60 calendar”
Source page 10

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 10
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

Set-aside

3 findings
Requirement 1Verified

No set-aside specified

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/8522769e61fa4b8e9ccca85a9f15254b /data2/solicitation/setAsideView official source ↗
“NONE”
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

Small business size

4 findings
Requirement 1Verified

$45,000,000

View source 1
01page 6View official source ↗
“Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.” Representations and Certifications – This solicitation is issued under NAICS 237310 – Highway, Street & Bridge Construction with a small business size standard of $45 million”
Source page 6

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 6
Requirement 2Needs confirmation

—

Needs confirmation

Applies to: subcontractor

View source 1
01page 150View official source ↗
“HUBZone, SDB, WOSB)4 4 List all applicable size standards for each proposed subcontractor.”
Source page 150

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 150
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

Required licenses

3 findings
Requirement 1Verified

(3) Copy of a valid blaster license accepted by the state where the project is located for the type of blasting required; and (4) Five references with knowledge of qualifications and reliability.

View source 1
01page 131View official source ↗
“(3) Copy of a valid blaster license accepted by the state where the project is located for the type of blasting required; and (4) Five references with knowledge of qualifications and reliability.”
Source page 131

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 131
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

Experience & references

6 findings
Requirement 1Needs confirmation

—

Needs confirmation

Applies when: at least 2 years’ experience in highway construction, inspection, quality control, and m

View source 1
01page 82View official source ↗
“Furnish a QCM who has at least 2 years’ experience in highway construction, inspection, quality control, and material testing.”
Source page 82

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 82
Requirement 2Needs confirmation

—

Needs confirmation

Applies when: at least 5 years

View source 1
01page 101View official source ↗
“(b) A résumé for each individual describing their knowledge and experience providing erosion and sediment control and pollution prevention on highway or road construction projects for at least 5 years.”
Source page 101

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 101
Requirement 3Needs confirmation

—

Needs confirmation

Applies when: at least 3 years’ experience in wave equation analyses to perform the wave equation anal

View source 1
01page 398View official source ↗
“Name of the engineer and a résumé describing at least 3 years’ experience in wave equation analyses to perform the wave equation analysis.”
Source page 398

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 398
Requirement 4Needs confirmation

—

Needs confirmation

Applies when: at least five projects of similar complexity

View source 1
01page 518View official source ↗
“Name and a résumé describing experience in shotcrete construction on at least five projects of similar complexity.”
Source page 518

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 518
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

Key personnel

Verified
Attach resumes of key personnel as well as the on-site manager(s) and superintendent(s), and specifically identify the following - Present position, responsibility, and length of employment - Amount and type of construction - Amount and type of highway construction experience, inRead full requirement Close full requirement

Attach resumes of key personnel as well as the on-site manager(s) and superintendent(s), and specifically identify the following - Present position, responsibility, and length of employment - Amount and type of construction - Amount and type of highway construction experience, in

Applies to: person

View source 1
01page 34View official source ↗
“Attach resumes of key personnel as well as the on-site manager(s) and superintendent(s), and specifically identify the following - Present position, responsibility, and length of employment - Amount and type of construction - Amount and type of highway construction experience, including position, re”
Source page 34

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 34

Financial capacity

2 findings
Requirement 1Verified

The Government may require the surety to furnish additional substantiating information concerning its financial capability. 4. Corporations executing the bond shall affix their corporate seals.

Applies to: surety

View source 1
01page 32View official source ↗
“The Government may require the surety to furnish additional substantiating information concerning its financial capability. 4. Corporations executing the bond shall affix their corporate seals.”
Source page 32

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 32
Requirement 2Verified

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury D

Applies to: surety

View source 1
01page 40View official source ↗
“(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulation”
Source page 40

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 40

Joint ventures & teaming

15 findings
Requirement 1Conflicting sources

—

Conflicting sources

View source 1
01page 24View official source ↗
“Authority to Bind Joint Venture This certifies that the person signing the proposal has the authority to actually bind the joint venture pursuant to its joint venture agreement, and that each of the named persons listed below individually has full authority to enter into and execute contractual inst”
Source page 24

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 24
Requirement 2Conflicting sources

—

Conflicting sources

View source 1
01page 24View official source ↗
“individually has full authority to enter into and execute contractual instruments on behalf of said joint venture, except as follows:”
Source page 24

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 24
Requirement 3Conflicting sources

—

Conflicting sources

View source 1
01page 27View official source ↗
“(d) Joint ventures.”
Source page 27

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 27
Requirement 4Conflicting sources

—

Conflicting sources

View source 1
01page 27View official source ↗
“Submit a copy of the Joint Venture agreement.”
Source page 27

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 27
Requirement 5Conflicting sources

—

Conflicting sources

View source 1
01page 27View official source ↗
“Sign the SF 1442 according to the Joint Venture agreement.”
Source page 27

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 27
Requirement 6Conflicting sources

—

Conflicting sources

View source 1
01page 34View official source ↗
“Provide the name of the home office addresses of each of the joint venture partners; indicate which partner is the sponsoring partner.”
Source page 34

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 34
Requirement 7Conflicting sources

—

Conflicting sources

View source 1
01page 39View official source ↗
“(c) Joint venture.”
Source page 39

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 39
Requirement 8Verified

may be ineligible for award of the contract. (Prime and subcontracting | U.S. Small Business

View source 1
01page 7View official source ↗
“may be ineligible for award of the contract. (Prime and subcontracting | U.S. Small Business”
Source page 7

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 7
Requirement 9Verified

INSTRUCTIONS: When the offeror/principal is a joint venture, include this certification

Applies when: When the offeror/principal is a joint venture, include this certification

View source 1
01page 24View official source ↗
“INSTRUCTIONS: When the offeror/principal is a joint venture, include this certification”
Source page 24

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 24
Requirement 10Verified
B-1 Bid Bond Date Bond Executed (Must Not Be Later OMB Control Number: 9000-0001 (See Instructions on Page 3) Than Bid Opening Date) Expiration Date: 1/31/2027 Principal (Legal Name And Business Address) Type Of Organization ("X" One) Individual Partnership Joint Venture CorporatRead full requirement Close full requirement

B-1 Bid Bond Date Bond Executed (Must Not Be Later OMB Control Number: 9000-0001 (See Instructions on Page 3) Than Bid Opening Date) Expiration Date: 1/31/2027 Principal (Legal Name And Business Address) Type Of Organization ("X" One) Individual Partnership Joint Venture Corporat

View source 1
01page 29View official source ↗
“B-1 Bid Bond Date Bond Executed (Must Not Be Later OMB Control Number: 9000-0001 (See Instructions on Page 3) Than Bid Opening Date) Expiration Date: 1/31/2027 Principal (Legal Name And Business Address) Type Of Organization ("X" One) Individual Partnership Joint Venture Corporation Other (Specify) ”
Source page 29

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 29
Requirement 11Verified

Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved. 3. The bond may express penal sum as a perc

Applies when: if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved

View source 1
01page 31View official source ↗
“Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved. 3. The bond may express penal sum as a percentage of the bid pr”
Source page 31

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 31
Requirement 12Verified

If the prospective bidder is a joint venture or general partnership, a separate Bidder's Qualifications form shall be provided individually for each joint venture participant or partner. 1. Name and address of business Name Unique Entity ID (See RFO Provision 52.204-91 Street Emp

Applies when: If the prospective bidder is a joint venture or general partnership, a separate Bidder's Qualifications form shall be provided individually for each joint venture participant or part

View source 1
01page 33View official source ↗
“If the prospective bidder is a joint venture or general partnership, a separate Bidder's Qualifications form shall be provided individually for each joint venture participant or partner. 1. Name and address of business Name Unique Entity ID (See RFO Provision 52.204-91 Street Employer ID Number (EIN”
Source page 33

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 33
Requirement 13Verified

Concern Concern Concern 3. If a Joint Venture or General Partnership:

Applies when: If a Joint Venture or General Partnership:

View source 1
01page 33View official source ↗
“Concern Concern Concern 3. If a Joint Venture or General Partnership:”
Source page 33

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 33
Requirement 14Verified

A HUBZone joint venture agrees that, in the performance of the contract, at least 40 percent of the aggregate work performed by the joint venture shall be completed by the HUBZone small business parties to the joint venture.

Applies when: work performed by the joint venture shall be completed by the HUBZone small business parties to the joint venture; at least 40 percent of the aggregate work performed by the joint venture shall be comple

View source 1
01page 39View official source ↗
“A HUBZone joint venture agrees that, in the performance of the contract, at least 40 percent of the aggregate work performed by the joint venture shall be completed by the HUBZone small business parties to the joint venture.”
Source page 39

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 39
Requirement 15Verified

Work performed by the HUBZone small business parties to the joint venture must be more than administrative functions.

Applies when: Work performed by the HUBZone small business parties to the joint venture

View source 1
01page 39View official source ↗
“Work performed by the HUBZone small business parties to the joint venture must be more than administrative functions.”
Source page 39

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 39

Exclusions & responsibility

Verified

(DEC 2014)(DEVIATION NOV 2025) 52.204-91 Contractor Identification (DEVIATION NOV 2025) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment.

Applies when: When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment

View source 1
01page 43View official source ↗
“(DEC 2014)(DEVIATION NOV 2025) 52.204-91 Contractor Identification (DEVIATION NOV 2025) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment.”
Source page 43

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 43

Prequalification

4 findings
Requirement 1Verified

Weld the entire pile cross-section using prequalified AWS groove weld butt joints.

View source 1
01page 406View official source ↗
“Weld the entire pile cross-section using prequalified AWS groove weld butt joints.”
Source page 406

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 406
Requirement 2Verified

Use a prequalified ASTM A775 patching/repair material to patch defects in the coating that are discernible to the unaided eye.

View source 1
01page 450View official source ↗
“Use a prequalified ASTM A775 patching/repair material to patch defects in the coating that are discernible to the unaided eye.”
Source page 450

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 450
Requirement 3Verified

Conform to AASHTO/AWS, Bridge Welding Code D1.5 (D1.5M) for welding, welder qualifications, prequalification of weld details, and inspection of welds.

View source 1
01page 466View official source ↗
“Conform to AASHTO/AWS, Bridge Welding Code D1.5 (D1.5M) for welding, welder qualifications, prequalification of weld details, and inspection of welds.”
Source page 466

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 466
Requirement 4Verified
The mean core grade must not be greater than the maximum permissible value shown in Table 566-1 with no individual core grade greater than 3. When a prequalification test panel is rejected by the CO, a second panel may be shot.Read full requirement Close full requirement

The mean core grade must not be greater than the maximum permissible value shown in Table 566-1 with no individual core grade greater than 3. When a prequalification test panel is rejected by the CO, a second panel may be shot.

Applies when: When a prequalification test panel is rejected by the CO, a second panel may be shot

View source 1
01page 522View official source ↗
“The mean core grade must not be greater than the maximum permissible value shown in Table 566-1 with no individual core grade greater than 3. When a prequalification test panel is rejected by the CO, a second panel may be shot.”
Source page 522

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 522

1 additional field have no reviewed finding.

02

Deadlines & submission

When and how to submit, and whether you are still in time.

15 verified6 to confirm

Response deadline

3 findings
Requirement 1Verified

2026-11-03T14:00:00-07:00

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/8522769e61fa4b8e9ccca85a9f15254b /data2/solicitation/deadlines/responseView official source ↗
“2026-11-03T14:00:00-07:00”
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

How to submit

4 findings
Requirement 1Verified

Submit the bid guarantee on SF 24, Bid Bond.

View source 1
01page 28View official source ↗
“Submit the bid guarantee on SF 24, Bid Bond.”
Source page 28

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 28
Requirement 2Verified

ATTACHMENT 1 – FHWA SUBCONTRACTING PLAN 1. INSTRUCTIONS: • Where subcontracting opportunities will not exist for the solicitation, the bidder/offeror shall submit a response outlining the rationale for making this determination with its proposal/bid.

View source 1
01page 149View official source ↗
“ATTACHMENT 1 – FHWA SUBCONTRACTING PLAN 1. INSTRUCTIONS: • Where subcontracting opportunities will not exist for the solicitation, the bidder/offeror shall submit a response outlining the rationale for making this determination with its proposal/bid.”
Source page 149

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 149
Requirement 3Verified

Submit a proposal for approval for other correction methods not listed above. 282

View source 1
01page 298View official source ↗
“Submit a proposal for approval for other correction methods not listed above. 282”
Source page 298

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 298
Missing information · 1 check
Not reviewed

—

Not reviewed — requirement not confirmed

Required submission files

3 findings
Requirement 1Verified

ATTACHMENT 1 – FHWA SUBCONTRACTING PLAN 1. INSTRUCTIONS: • Where subcontracting opportunities will not exist for the solicitation, the bidder/offeror shall submit a response outlining the rationale for making this determination with its proposal/bid.

View source 1
01page 149View official source ↗
“ATTACHMENT 1 – FHWA SUBCONTRACTING PLAN 1. INSTRUCTIONS: • Where subcontracting opportunities will not exist for the solicitation, the bidder/offeror shall submit a response outlining the rationale for making this determination with its proposal/bid.”
Source page 149

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 149
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

Acknowledge amendments

3 findings
Requirement 1Verified

Item 19: ACKNOWLEDGMENT OF AMENDMENTS: FAILURE TO

View source 1
01page 11View official source ↗
“Item 19: ACKNOWLEDGMENT OF AMENDMENTS: FAILURE TO”
Source page 11

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 11
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

Procurement contact

Verified

Kelly Palmer · cflacquisitions@dot.gov

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/8522769e61fa4b8e9ccca85a9f15254b /data2/pointOfContact/0View official source ↗
“Kelly Palmer · cflacquisitions@dot.gov”

Bid opening

6 findings
Requirement 1Needs confirmation

—

Needs confirmation

Applies when: If this is a sealed bid solicitation, offers will be publicly opened at that time

View source 1
01page 9View official source ↗
“If this is a sealed bid solicitation, offers will be publicly opened at that time.”
Source page 9

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 9
Requirement 2Needs confirmation

—

Needs confirmation

Applies when: within 14 days after the opening of bidsMust be met by: within 14 days after the opening of bids

Applies to: surety

View source 1
01page 28View official source ↗
“Furnish documentary evidence as to the ownership and value of the assets pledged in support of the bond and details of the security interest in the assets by the individual sureties for the apparent low bidder within 14 days after the opening of bids.”
Source page 28

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 28
Requirement 3Needs confirmation

—

Needs confirmation

View source 1
01page 29View official source ↗
“Section 102 102.05 Public Opening of Bids.”
Source page 29

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 29
Requirement 4Needs confirmation

—

Needs confirmation

View source 1
01page 29View official source ↗
“Bids will be publicly opened at the time specified in the SF 1442, Solicitation, Offer, and Award.”
Source page 29

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 29
Requirement 5Needs confirmation

—

Needs confirmation

View source 1
01page 40View official source ↗
“(SEP 1996) (a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.”
Source page 40

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 40
Requirement 6Needs confirmation

—

Needs confirmation

Applies when: upon execution of contractual documents and bonds (including any necessary coinsuranMust be met by: upon execution of contractual documents and bonds (including any necessary coinsuran

View source 1
01page 40View official source ↗
“The Contracting Officer will return bid guarantees, other than bid bonds - (1) To unsuccessful bidders as soon as practicable after the opening of bids; and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements),”
Source page 40

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 40

Mandatory forms

3 findings
Requirement 1Verified

Submit a printed copy of your bid to the address listed on the SF-1442 (Page A-1, Item 8).

View source 1
01page 4View official source ↗
“Submit a printed copy of your bid to the address listed on the SF-1442 (Page A-1, Item 8).”
Source page 4

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 4
Requirement 2Verified
Submit the following documents with your Bid Package– • SF-1442, Solicitation, Offer & Award, Pages A-1 and A-2 • Indication of interest in formal Partnering, Page A-5 • Bid Schedule Pages A-6 through A-12 • Completed an applicable Authority to Bind certificate, pages A-13 througRead full requirement Close full requirement

Submit the following documents with your Bid Package– • SF-1442, Solicitation, Offer & Award, Pages A-1 and A-2 • Indication of interest in formal Partnering, Page A-5 • Bid Schedule Pages A-6 through A-12 • Completed an applicable Authority to Bind certificate, pages A-13 throug

View source 1
01page 4View official source ↗
“Submit the following documents with your Bid Package– • SF-1442, Solicitation, Offer & Award, Pages A-1 and A-2 • Indication of interest in formal Partnering, Page A-5 • Bid Schedule Pages A-6 through A-12 • Completed an applicable Authority to Bind certificate, pages A-13 through A-17 • Buy America”
Source page 4

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 4
Requirement 3Verified

Item 19: ACKNOWLEDGMENT OF AMENDMENTS: FAILURE TO ACKNOWLEDGE AMENDMENTS, IN ITEM 19 OF THE SF-1442, BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID.

View source 1
01page 11View official source ↗
“Item 19: ACKNOWLEDGMENT OF AMENDMENTS: FAILURE TO ACKNOWLEDGE AMENDMENTS, IN ITEM 19 OF THE SF-1442, BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID.”
Source page 11

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 11

Grounds for rejection

5 findings
Requirement 1Verified

Photocopies and Faxed copies are NOT acceptable and will make your bid non-responsive.

View source 1
01page 4View official source ↗
“Photocopies and Faxed copies are NOT acceptable and will make your bid non-responsive.”
Source page 4

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 4
Requirement 2Verified

Failure of the surety to respond with the requested documentation within 7 days of receipt of the request is cause for rejection of the surety.

Applies when: within 7 days of receipt of the request is cause for rejection of the suretyMust be met by: within 7 days of receipt of the request is cause for rejection of the surety

Applies to: surety

View source 1
01page 28View official source ↗
“Failure of the surety to respond with the requested documentation within 7 days of receipt of the request is cause for rejection of the surety.”
Source page 28

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 28
Requirement 3Verified

Any material misstatement by the surety, overstatement of assets (either as to ownership or value), or understatement of liabilities is cause for rejection of the surety.

Applies to: surety

View source 1
01page 28View official source ↗
“Any material misstatement by the surety, overstatement of assets (either as to ownership or value), or understatement of liabilities is cause for rejection of the surety.”
Source page 28

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 28
Requirement 4Verified

Failure of the surety to accept such mail or failure of the surety to respond with the requested information or documents within 7 days of receipt of the request; will be cause for rejection of the surety.

Applies when: within 7 days of receipt of the requestMust be met by: within 7 days of receipt of the request

Applies to: surety

View source 1
01page 28View official source ↗
“Failure of the surety to accept such mail or failure of the surety to respond with the requested information or documents within 7 days of receipt of the request; will be cause for rejection of the surety.”
Source page 28

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 28
Requirement 5Verified

(SEP 1996) (a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

View source 1
01page 40View official source ↗
“(SEP 1996) (a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.”
Source page 40

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 40
Missing information4 checks · expand to review

A missing value is not a waiver. Check the source or ask the agency before relying on it.

Questions due

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

Site visit / pre-bid meeting

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

4 additional fields have no reviewed finding.

Continue your review

6 more sections are available once you sign in

Pricing & payment · Bonds & insurance · Evaluation & award · Scope & delivery · Labor, sourcing & compliance · Contract terms & risk

Sign in — free

Extracted from the public documents linked above. This is an information aid, not a determination of bid eligibility or legal advice. Verify the original wording and any addenda before submitting a bid.

$5.0M – $10M
11 days left
See all 14