DEPT OF DEFENSE · Dongducheon, KR-41
Cleaning of Food Service Exhaust Fans and Ducts for Dining Facilities in USAG Yongsan-Casey.
- Response deadline
- 6 days left
- Published project value
- Not confirmedCheck the pricing and payment terms below.
- Solicitation number
- W90VN827RA001
Dates to plan around
Times follow the original source.
- Response deadline
Source wording
2026-10-30T11:00:00+09:00
9 documents found72% of weighted requirement checks reviewed
Review first
Start with these requirements and unresolved points.- Must doExclusions & responsibility
View 1 flagged requirement
- Requirement 1 ↗
The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered defense telecommunications equipment or services".
- Requirement 1 ↗
- Must doKey personnel
View 7 flagged requirements
- Requirement 1 ↗
The PM's resume must clearly identify as required below: - Associate degree or bachelor's degree from an accredited college or university - Proposed position title
- Requirement 2 ↗
The Electrical Engineer's resume must clearly identify as required below: - Education from a Related Two (2) or Four (4) year college program as Electrical Engineering - One (1) year of experience with the last five (5) years from the solicitation closing date as labor for cleani
- Requirement 3 ↗
At a minimum, the resume shall include the PM's full name, description of qualifying work experience, period of experience, value or size of contract or project, company name or employer, and validating point of contact information.
- Requirement 4 ↗
resume must clearly identify as required below:
- Requirement 5 ↗
The offeror shall submit the PM's resume demonstrating relevant experience performing or managing food service exhaust system cleaning services and a copy of valid Annual Hygiene Training Certification issued by the Korean Facility Hygiene Management Association for Cy26. At a mi
- Requirement 6 ↗
The PM's resume must clearly identify as required below: - Associate degree or bachelor's degree from an accredited college or university - Proposed position title - A brief description of work experience - Company name, phone number, and complete name of the employer - Length of
- Requirement 7 ↗
The Electrical Engineer's resume must clearly identify as required below:
- Requirement 1 ↗
- Must doRegistrations
View 4 flagged requirements
- Requirement 1 ↗
All ve- hicles must be registered in accordance with current local requirements. 2.5.1.3.1 Contractor and Vendor Access.
- Requirement 2 ↗
All vehicles must be registered in accordance with current local require- ments in which they are registered. 2.5.1.3.2 All Contractor personnel, not possessing a Common Access Card (CAC), request- ing access to USAG Yongsan-Casey will enter through the designated Visitor Control
- Requirement 3 ↗
To access WAWF, the Contractor shall- (1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and (2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration availa
- Requirement 4 ↗
(1) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "Unique Entity Identifier" followed by the UEI that identifies the Offeror's name and address exactly as stated in the offer.
- Requirement 1 ↗
Eligibility & participation
Whether you can bid at all, and what you must already hold.
Registrations
9 findingsAll ve- hicles must be registered in accordance with current local requirements. 2.5.1.3.1 Contractor and Vendor Access.
View source 2
“All ve- hicles must be registered in accordance with current local requirements. 2.5.1.3.1 Contractor and Vendor Access.”
Source page 14
Page markings may include other requirements. The quotation above identifies this requirement.

“All ve- hicles must be registered in accordance with current local requirements. 2.5.1.3.1 Contractor and Vendor Access.”
Source page 14
Page markings may include other requirements. The quotation above identifies this requirement.

All vehicles must be registered in accordance with current local require- ments in which they are registered. 2.5.1.3.2 All Contractor personnel, not possessing a Common Access Card (CAC), request- ing access to USAG Yongsan-Casey will enter through the designated Visitor Control
View source 2
“All vehicles must be registered in accordance with current local require- ments in which they are registered. 2.5.1.3.2 All Contractor personnel, not possessing a Common Access Card (CAC), request- ing access to USAG Yongsan-Casey will enter through the designated Visitor Control Center (VCC).”
Source page 14
Page markings may include other requirements. The quotation above identifies this requirement.

“All vehicles must be registered in accordance with current local require- ments in which they are registered. 2.5.1.3.2 All Contractor personnel, not possessing a Common Access Card (CAC), request- ing access to USAG Yongsan-Casey will enter through the designated Visitor Control Center (VCC).”
Source page 14
Page markings may include other requirements. The quotation above identifies this requirement.

To access WAWF, the Contractor shall- (1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and (2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration availa
View source 1
“To access WAWF, the Contractor shall- (1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and (2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site”
Source page 14
Page markings may include other requirements. The quotation above identifies this requirement.

(Deviation 2026-02 2026-O0038) Offeror Identification (Feb 2026) (Deviation 2026-O0038) If the Offeror will not have an active Federal Government contracts registration in the System for Award Management (https://www.sam.gov) when submitting its offer, it shall complete paragraph
Applies when: If the Offeror will not have an active Federal Government contracts registration in the System for Award Management (https://www
View source 1
“(Deviation 2026-02 2026-O0038) Offeror Identification (Feb 2026) (Deviation 2026-O0038) If the Offeror will not have an active Federal Government contracts registration in the System for Award Management (https://www.sam.gov) when submitting its offer, it shall complete paragraphs (c) and (d) of thi”
Source page 40
Page markings may include other requirements. The quotation above identifies this requirement.

(1) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "Unique Entity Identifier" followed by the UEI that identifies the Offeror's name and address exactly as stated in the offer.
View source 1
“(1) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "Unique Entity Identifier" followed by the UEI that identifies the Offeror's name and address exactly as stated in the offer.”
Source page 41
Page markings may include other requirements. The quotation above identifies this requirement.

(1) The Offeror shall provide its CAGE code with its offer with its name and location address or otherwise include it prominently in its offer.
View source 1
“(1) The Offeror shall provide its CAGE code with its offer with its name and location address or otherwise include it prominently in its offer.”
Source page 43
Page markings may include other requirements. The quotation above identifies this requirement.

Agency (NSPA) ( https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx) (2) The Offeror shall provide the CAGE code and legal business name (Do not use a "doing
View source 1
“Agency (NSPA) ( https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx) (2) The Offeror shall provide the CAGE code and legal business name (Do not use a "doing”
Source page 43
Page markings may include other requirements. The quotation above identifies this requirement.

Missing information · 2 checks
—
Not reviewed — requirement not confirmed
—
Not found in reviewed sources
Set-aside
3 findingsHUBZONE
View source 1
“TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/ 7.FOR SOLICITATION calls) LOCAL TIME INFORMATION CALL: 9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR: SMALL BUSINESS WOMEN-OWNED SMALL NORTH AMERICAN HUBZONE SMALL BUSINESS (WOSB) INDUSTRY CLASSIFICATION BUSINESS ECONOMICALLY STANDARD (NAICS):”
Source page 1
Page markings may include other requirements. The quotation above identifies this requirement.

Missing information · 2 checks
—
Not reviewed — requirement not confirmed
—
Not found in reviewed sources
Small business size
3 findings—
Needs confirmation
View source 1
“VETERAN-OWNED WOMEN-OWNED SMALL SIZE STANDARD:”
Source page 1
Page markings may include other requirements. The quotation above identifies this requirement.

Missing information · 2 checks
—
Not reviewed — requirement not confirmed
—
Not found in reviewed sources
Experience & references
7 findings—
Needs confirmation
Applies when: at least two (2) years of project management experience
Applies to: person
View source 1
“Project Manager: The offeror shall be evaluated on their submitted resume of Project Manager (PM) with at least two (2) years of project management experience.”
Source page 4
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
Applies when: within the last five (5) years from the solicitation closing date for food duct cleani
View source 2
“TE-04 Contractor Qualifications Contractor Qualification: The prime contractor shall have a minimum of two (2) years of experience within the last five (5) years from the solicitation closing date for food duct cleaning service or related lines of business.”
Source page 8
Page markings may include other requirements. The quotation above identifies this requirement.

“TE-04 Contractor Qualifications Contractor Qualification: The prime contractor shall have a minimum of two (2) years of experience within the last five (5) years from the solicitation closing date for food duct cleaning service or related lines of business.”
Source page 8
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
Applies when: At least one (1) year of experience within the last five (5) years from the solicitation
View source 2
“Experience: At least one (1) year of experience within the last five (5) years from the solicitation closing date as the Labor on Cleaning of Food Service Exhaust Fans and Ducts for Dining Facilities contract.”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

“Experience: At least one (1) year of experience within the last five (5) years from the solicitation closing date as the Labor on Cleaning of Food Service Exhaust Fans and Ducts for Dining Facilities contract.”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
Applies when: within the last five (5) years on contracts for cleaning food service exhaust systems
Applies to: person
View source 1
“The proposed Project Manager shall have an associate degree or bachelor's degree from an accredited college or university and a minimum of two (2) years of project management experience within the last five (5) years on contracts for cleaning food service exhaust systems (hoods, fans, and ducts).”
Source page 23
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
Applies when: at least one (1) year of experience within the last five (5) years from the solicitation
View source 1
“The proposed Electrical Industrial Engineer shall have at least one (1) year of experience within the last five (5) years from the solicitation closing date as labor for cleaning food service exhaust fans and ducts for dining facility contracts.”
Source page 25
Page markings may include other requirements. The quotation above identifies this requirement.

Missing information · 2 checks
—
Not reviewed — requirement not confirmed
—
Not found in reviewed sources
Key personnel
24 findingsThe Government will evaluate offers based on the following factors, listed in descending order of importance. : Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key PersonnelClose full requirement
The Government will evaluate offers based on the following factors, listed in descending order of importance. : Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key Personnel
Applies to: person
View source 1
“The Government will evaluate offers based on the following factors, listed in descending order of importance. : Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key Personnel”
Source page 3
Page markings may include other requirements. The quotation above identifies this requirement.

(2) Subfactor 2: Key Personnel
Applies to: person
View source 3
“(2) Subfactor 2: Key Personnel”
Source page 4
Page markings may include other requirements. The quotation above identifies this requirement.

“(2) Subfactor 2: Key Personnel”
Source page 18
Page markings may include other requirements. The quotation above identifies this requirement.

“(2) Subfactor 2: Key Personnel”
Source page 28
Page markings may include other requirements. The quotation above identifies this requirement.

The PM's resume must clearly identify as required below: - Associate degree or bachelor's degree from an accredited college or university - Proposed position title
View source 1
“The PM's resume must clearly identify as required below: - Associate degree or bachelor's degree from an accredited college or university - Proposed position title”
Source page 4
Page markings may include other requirements. The quotation above identifies this requirement.

The Electrical Engineer's resume must clearly identify as required below: - Education from a Related Two (2) or Four (4) year college program as Electrical Engineering - One (1) year of experience with the last five (5) years from the solicitation closing date as labor for cleani
View source 2
“The Electrical Engineer's resume must clearly identify as required below: - Education from a Related Two (2) or Four (4) year college program as Electrical Engineering - One (1) year of experience with the last five (5) years from the solicitation closing date as labor for cleaning food service exha”
Source page 5
Page markings may include other requirements. The quotation above identifies this requirement.

“The Electrical Engineer's resume must clearly identify as required below: - Education from a Related Two (2) or Four (4) year college program as Electrical Engineering - One (1) year of experience with the last five (5) years from the solicitation closing date as labor for cleaning food service exha”
Source page 19
Page markings may include other requirements. The quotation above identifies this requirement.

The transition plan will have a ten (10) calendar days transition period that will be implemented by the Contractor and shall state Con- tractor key personnel on board, to include IT/Network accounts and access with the appropriate Government organizations.
Applies to: person
View source 2
“The transition plan will have a ten (10) calendar days transition period that will be implemented by the Contractor and shall state Con- tractor key personnel on board, to include IT/Network accounts and access with the appropriate Government organizations.”
Source page 7
Page markings may include other requirements. The quotation above identifies this requirement.

“The transition plan will have a ten (10) calendar days transition period that will be implemented by the Contractor and shall state Con- tractor key personnel on board, to include IT/Network accounts and access with the appropriate Government organizations.”
Source page 7
Page markings may include other requirements. The quotation above identifies this requirement.

The plan shall contain details that include but are not limited to; timelines for events, key personnel involved and interface with the Government and follow-on Contractor.
Applies to: person
View source 2
“The plan shall contain details that include but are not limited to; timelines for events, key personnel involved and interface with the Government and follow-on Contractor.”
Source page 7
Page markings may include other requirements. The quotation above identifies this requirement.

“The plan shall contain details that include but are not limited to; timelines for events, key personnel involved and interface with the Government and follow-on Contractor.”
Source page 7
Page markings may include other requirements. The quotation above identifies this requirement.

Retention of key personnel;
Applies to: person
View source 2
“Retention of key personnel;”
Source page 7
Page markings may include other requirements. The quotation above identifies this requirement.

“Retention of key personnel;”
Source page 7
Page markings may include other requirements. The quotation above identifies this requirement.

Contractor Employees. Key Personnel.
Applies to: person
View source 2
“Contractor Employees. Key Personnel.”
Source page 8
Page markings may include other requirements. The quotation above identifies this requirement.

“Contractor Employees. Key Personnel.”
Source page 8
Page markings may include other requirements. The quotation above identifies this requirement.

Sub-Factor 2: Key Personnel
Applies to: person
View source 3
“Sub-Factor 2: Key Personnel”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

“Sub-Factor 2: Key Personnel”
Source page 23
Page markings may include other requirements. The quotation above identifies this requirement.

“Sub-Factor 2: Key Personnel”
Source page 22
Page markings may include other requirements. The quotation above identifies this requirement.

Subfactor 2: Key
View source 3
“Subfactor 2: Key”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

“Subfactor 2: Key”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

“Subfactor 2: Key”
Source page 22
Page markings may include other requirements. The quotation above identifies this requirement.

The Project Manager shall be available after normal hours to serve as the central point of contact for Contractor operations.
Applies to: person
View source 2
“The Project Manager shall be available after normal hours to serve as the central point of contact for Contractor operations.”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

“The Project Manager shall be available after normal hours to serve as the central point of contact for Contractor operations.”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

Sub-factor 2. Key Personnel: (1) Project Manager (PM): The offeror shall provide a qualified Project Manager (PM) who will be responsible for the overall performance of the work.
Applies to: person
View source 3
“Sub-factor 2. Key Personnel: (1) Project Manager (PM): The offeror shall provide a qualified Project Manager (PM) who will be responsible for the overall performance of the work.”
Source page 10
Page markings may include other requirements. The quotation above identifies this requirement.

“Sub-factor 2. Key Personnel: (1) Project Manager (PM): The offeror shall provide a qualified Project Manager (PM) who will be responsible for the overall performance of the work.”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

“Sub-factor 2. Key Personnel: (1) Project Manager (PM): The offeror shall provide a qualified Project Manager (PM) who will be responsible for the overall performance of the work.”
Source page 23
Page markings may include other requirements. The quotation above identifies this requirement.

The proposed Project Manager shall have an associate degree or bachelor's degree from an accredited college or university and a minimum of two (2) years of project management experience within the last five (5) years on contracts for cleaning food service exhaust systems (hoods,
Applies when: within the last five (5) years on contracts for cleaning food service exhaust systems
Applies to: person
View source 2
“The proposed Project Manager shall have an associate degree or bachelor's degree from an accredited college or university and a minimum of two (2) years of project management experience within the last five (5) years on contracts for cleaning food service exhaust systems (hoods, fans, and ducts).”
Source page 10
Page markings may include other requirements. The quotation above identifies this requirement.

“The proposed Project Manager shall have an associate degree or bachelor's degree from an accredited college or university and a minimum of two (2) years of project management experience within the last five (5) years on contracts for cleaning food service exhaust systems (hoods, fans, and ducts).”
Source page 23
Page markings may include other requirements. The quotation above identifies this requirement.

At a minimum, the resume shall include the PM's full name, description of qualifying work experience, period of experience, value or size of contract or project, company name or employer, and validating point of contact information.
View source 2
“At a minimum, the resume shall include the PM's full name, description of qualifying work experience, period of experience, value or size of contract or project, company name or employer, and validating point of contact information.”
Source page 10
Page markings may include other requirements. The quotation above identifies this requirement.

“At a minimum, the resume shall include the PM's full name, description of qualifying work experience, period of experience, value or size of contract or project, company name or employer, and validating point of contact information.”
Source page 23
Page markings may include other requirements. The quotation above identifies this requirement.

N/A. 2.1.11 Contractor Employees. 2.1.11.1 Key Personnel. 2.1.11.1.1 Project Manager (PM).
Applies to: person
View source 2
“N/A. 2.1.11 Contractor Employees. 2.1.11.1 Key Personnel. 2.1.11.1.1 Project Manager (PM).”
Source page 11
Page markings may include other requirements. The quotation above identifies this requirement.

“N/A. 2.1.11 Contractor Employees. 2.1.11.1 Key Personnel. 2.1.11.1.1 Project Manager (PM).”
Source page 11
Page markings may include other requirements. The quotation above identifies this requirement.

The PM and any individuals designated as key personnel shall be able to understand, speak, read, and write the English language. 2.1.11.1.2 GFEBS PM Coordinator Lead.
Applies to: person
View source 2
“The PM and any individuals designated as key personnel shall be able to understand, speak, read, and write the English language. 2.1.11.1.2 GFEBS PM Coordinator Lead.”
Source page 12
Page markings may include other requirements. The quotation above identifies this requirement.

“The PM and any individuals designated as key personnel shall be able to understand, speak, read, and write the English language. 2.1.11.1.2 GFEBS PM Coordinator Lead.”
Source page 12
Page markings may include other requirements. The quotation above identifies this requirement.

W90VN827RA0010001 Page 18 of 32 Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key Personnel Factor 2. Past Performance Factor 3. Price Factor 1. Technical Approach Technical capability will be Close full requirement
W90VN827RA0010001 Page 18 of 32 Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key Personnel Factor 2. Past Performance Factor 3. Price Factor 1. Technical Approach Technical capability will be
Applies to: person
View source 1
“W90VN827RA0010001 Page 18 of 32 Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key Personnel Factor 2. Past Performance Factor 3. Price Factor 1. Technical Approach Technical capability will be evaluated to assess ”
Source page 18
Page markings may include other requirements. The quotation above identifies this requirement.

resume must clearly identify as required below:
View source 1
“resume must clearly identify as required below:”
Source page 19
Page markings may include other requirements. The quotation above identifies this requirement.

Waste is generated by educational, health care, correctional and other institutional facilities. 7.1.1.43 Key Personnel.
Applies to: person
View source 2
“Waste is generated by educational, health care, correctional and other institutional facilities. 7.1.1.43 Key Personnel.”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

“Waste is generated by educational, health care, correctional and other institutional facilities. 7.1.1.43 Key Personnel.”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the people who are listed in the proposal. 7.1.1.44 Lavatories, Latrines, or Bathrooms.Close full requirement
When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the people who are listed in the proposal. 7.1.1.44 Lavatories, Latrines, or Bathrooms.
Applies when: When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the people who are listed in the prop
Applies to: person
View source 2
“When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the people who are listed in the proposal. 7.1.1.44 Lavatories, Latrines, or Bathrooms.”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

“When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the people who are listed in the proposal. 7.1.1.44 Lavatories, Latrines, or Bathrooms.”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

The offeror shall submit the PM's resume demonstrating relevant experience performing or managing food service exhaust system cleaning services and a copy of valid Annual Hygiene Training Certification issued by the Korean Facility Hygiene Management Association for Cy26. At a mi
View source 1
“The offeror shall submit the PM's resume demonstrating relevant experience performing or managing food service exhaust system cleaning services and a copy of valid Annual Hygiene Training Certification issued by the Korean Facility Hygiene Management Association for Cy26. At a minimum, the resume sh”
Source page 25
Page markings may include other requirements. The quotation above identifies this requirement.

The Government will evaluate offers based on the following factors, listed in descending order of importance. : Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key Personnel Factor 2. Past PerforClose full requirement
The Government will evaluate offers based on the following factors, listed in descending order of importance. : Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key Personnel Factor 2. Past Perfor
Applies to: person
View source 1
“The Government will evaluate offers based on the following factors, listed in descending order of importance. : Evaluation Criteria: Factor 1. Technical Capability Subfactor (1), Prime Contractor's Registration and Certifications Subfactor (2), Key Personnel Factor 2. Past Performance Factor 3. Pric”
Source page 27
Page markings may include other requirements. The quotation above identifies this requirement.

The PM's resume must clearly identify as required below: - Associate degree or bachelor's degree from an accredited college or university - Proposed position title - A brief description of work experience - Company name, phone number, and complete name of the employer - Length of
View source 1
“The PM's resume must clearly identify as required below: - Associate degree or bachelor's degree from an accredited college or university - Proposed position title - A brief description of work experience - Company name, phone number, and complete name of the employer - Length of work experience (ye”
Source page 28
Page markings may include other requirements. The quotation above identifies this requirement.

The Electrical Engineer's resume must clearly identify as required below:
View source 1
“The Electrical Engineer's resume must clearly identify as required below:”
Source page 28
Page markings may include other requirements. The quotation above identifies this requirement.

Joint ventures & teaming
There may be more than one immediate owner (e.g., joint ventures).
View source 1
“There may be more than one immediate owner (e.g., joint ventures).”
Source page 41
Page markings may include other requirements. The quotation above identifies this requirement.

Exclusions & responsibility
3 findings(Deviation 2026- O0038) (Alternate I) 52.204-91 Contractor Identification. 2026-02 (Deviation 2026-O0038) 52.209-6 Protecting the Government's 2026-02 Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded.Close full requirement
(Deviation 2026- O0038) (Alternate I) 52.204-91 Contractor Identification. 2026-02 (Deviation 2026-O0038) 52.209-6 Protecting the Government's 2026-02 Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded.
Applies when: When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded
View source 1
“(Deviation 2026- O0038) (Alternate I) 52.204-91 Contractor Identification. 2026-02 (Deviation 2026-O0038) 52.209-6 Protecting the Government's 2026-02 Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded.”
Source page 32
Page markings may include other requirements. The quotation above identifies this requirement.

The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered defense telecommunications equipment or services".
View source 1
“The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered defense telecommunications equipment or services".”
Source page 45
Page markings may include other requirements. The quotation above identifies this requirement.

The Offeror shall review the list of excluded parties in the System for Award Management (SAM) at https://www.sam.gov for entities that are excluded when providing any equipment, system, or service to carry out covered missions that uses covered defense telecommunications equipme
Applies when: when providing any equipment, system, or service to carry out covered missions that uses covered defense telecommunications equipment or services as a substantial or essen
View source 1
“The Offeror shall review the list of excluded parties in the System for Award Management (SAM) at https://www.sam.gov for entities that are excluded when providing any equipment, system, or service to carry out covered missions that uses covered defense telecommunications equipment or services as a ”
Source page 46
Page markings may include other requirements. The quotation above identifies this requirement.

Conflicts of interest
NLT Not Later Than OCI Organizational Conflict of Interest
View source 2
“NLT Not Later Than OCI Organizational Conflict of Interest”
Source page 30
Page markings may include other requirements. The quotation above identifies this requirement.

“NLT Not Later Than OCI Organizational Conflict of Interest”
Source page 30
Page markings may include other requirements. The quotation above identifies this requirement.

Missing information2 checks · expand to review
A missing value is not a waiver. Check the source or ask the agency before relying on it.
Required licenses
2 findings—
Not reviewed — requirement not confirmed
—
Not found in reviewed sources
2 additional fields have no reviewed finding.
Deadlines & submission
When and how to submit, and whether you are still in time.
Response deadline
3 findings2026-10-30T11:00:00+09:00
View source 1
“2026-10-30T11:00:00+09:00”
Missing information · 2 checks
—
Not found in reviewed sources
—
Not reviewed — requirement not confirmed
How to submit
3 findingsW90VN827RA001 Page 2 of 52 Section A - Solicitation/Contract Form Instrument Name:Cleaning of Food Service Exhaust Fans and Ducts for Dining Facilities in USAG Yongsan-Casey Product Service Code : J073 SPECIAL NOTICE "All sources may submit a proposal or quote as applicable.Close full requirement
W90VN827RA001 Page 2 of 52 Section A - Solicitation/Contract Form Instrument Name:Cleaning of Food Service Exhaust Fans and Ducts for Dining Facilities in USAG Yongsan-Casey Product Service Code : J073 SPECIAL NOTICE "All sources may submit a proposal or quote as applicable.
View source 1
“W90VN827RA001 Page 2 of 52 Section A - Solicitation/Contract Form Instrument Name:Cleaning of Food Service Exhaust Fans and Ducts for Dining Facilities in USAG Yongsan-Casey Product Service Code : J073 SPECIAL NOTICE "All sources may submit a proposal or quote as applicable.”
Source page 2
Page markings may include other requirements. The quotation above identifies this requirement.

Missing information · 2 checks
—
Not found in reviewed sources
—
Not reviewed — requirement not confirmed
Required submission files
3 findingsThese licens- ing and certification shall maintain throughout the life of contract, and a copy of it shall be submitted to the Contracting Officer as a part of technical proposal.
View source 2
“These licens- ing and certification shall maintain throughout the life of contract, and a copy of it shall be submitted to the Contracting Officer as a part of technical proposal.”
Source page 8
Page markings may include other requirements. The quotation above identifies this requirement.

“These licens- ing and certification shall maintain throughout the life of contract, and a copy of it shall be submitted to the Contracting Officer as a part of technical proposal.”
Source page 8
Page markings may include other requirements. The quotation above identifies this requirement.

Missing information · 2 checks
—
Not found in reviewed sources
—
Not reviewed — requirement not confirmed
Procurement contact
16 findingsSe Yong Kwon · seyong.kwon.ln@army.mil · 3157224863
View source 1
“Se Yong Kwon · seyong.kwon.ln@army.mil · 3157224863”
Susie M. Lee · susie.m.lee3.civ@army.mil
View source 1
“Susie M. Lee · susie.m.lee3.civ@army.mil”
—
Needs confirmation
Applies when: prior to outages that will impact the function of the system, special problems or circumMust be met by: prior to outages that will impact the function of the system, special problems or circum
View source 2
“The Contractor shall inform the Fire Department point of contact (POC), prior to outages that will impact the function of the system, special problems or circumstances, which require Fire Department inspection.”
Source page 6
Page markings may include other requirements. The quotation above identifies this requirement.

“The Contractor shall inform the Fire Department point of contact (POC), prior to outages that will impact the function of the system, special problems or circumstances, which require Fire Department inspection.”
Source page 6
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
Applies to: person
View source 2
“The Project Manager shall be available after normal hours to serve as the central point of contact for Contractor operations.”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

“The Project Manager shall be available after normal hours to serve as the central point of contact for Contractor operations.”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 2
“At a minimum, the resume shall include the PM's full name, description of qualifying work experience, period of experience, value or size of contract or project, company name or employer, and validating point of contact information.”
Source page 10
Page markings may include other requirements. The quotation above identifies this requirement.

“At a minimum, the resume shall include the PM's full name, description of qualifying work experience, period of experience, value or size of contract or project, company name or employer, and validating point of contact information.”
Source page 23
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 2
“For each Past Performance submission, provide: The title of the contract/project A description of work completed Name of the Client Organization or Requiring Activity Length of contract/project (year/month/date - year/month/date) Value of contract/project Complete name, e-mail, and phone number of p”
Source page 11
Page markings may include other requirements. The quotation above identifies this requirement.

“For each Past Performance submission, provide: The title of the contract/project A description of work completed Name of the Client Organization or Requiring Activity Length of contract/project (year/month/date - year/month/date) Value of contract/project Complete name, e-mail, and phone number of p”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 1
“To access WAWF, the Contractor shall- (1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and (2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site”
Source page 14
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 1
“(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed”
Source page 14
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 1
“(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving”
Source page 15
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
Applies when: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42
View source 1
“W90VN827RA001 Page 17 of 52 (**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).) (4) Payment request.”
Source page 17
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 1
“(g) WAWF point of contact.”
Source page 17
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 1
“(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.”
Source page 17
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 1
“include the PM's full name, description of qualifying work experience, period of experience, value or size of contract or project, company name or employer, and validating point of contact”
Source page 25
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 1
“W90VN827RA0010001 Page 26 of 32 Value of contract/project Complete name, e-mail, and phone number of point of contact (POC) at Client Organization (b) The Government may send a Past Performance Questionnaire to the POC listed by the Offeror for each relevant contract, who will subsequently be reques”
Source page 26
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 2
“PM Preventive Maintenance POC Point of Contact”
Source page 30
Page markings may include other requirements. The quotation above identifies this requirement.

“PM Preventive Maintenance POC Point of Contact”
Source page 30
Page markings may include other requirements. The quotation above identifies this requirement.

—
Needs confirmation
View source 1
“Point of Contact: SIM, SANG YIM 722-4146”
Source page 48
Page markings may include other requirements. The quotation above identifies this requirement.

Formatting & signatures
8 findingsVolume Factor Title Page Limits I. 1 Technical Approach, Overall Page Limit: Twenty (20) single-sided Subfactor 1: Prime pages Contractor's Registrations & Resumes: Required for all Key Certifications Personnel.
View source 2
“Volume Factor Title Page Limits I. 1 Technical Approach, Overall Page Limit: Twenty (20) single-sided Subfactor 1: Prime pages Contractor's Registrations & Resumes: Required for all Key Certifications Personnel.”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

“Volume Factor Title Page Limits I. 1 Technical Approach, Overall Page Limit: Twenty (20) single-sided Subfactor 1: Prime pages Contractor's Registrations & Resumes: Required for all Key Certifications Personnel.”
Source page 22
Page markings may include other requirements. The quotation above identifies this requirement.

Personnel Excluded from Overall Page Limit: Table of
View source 2
“Personnel Excluded from Overall Page Limit: Table of”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

“Personnel Excluded from Overall Page Limit: Table of”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

Subfactor 2: Key Personnel Excluded from Overall Page Limit: Table of Contents, Cover Letter, and Resumes II. 2 Past Performance Maximum Overall Page Limit: Five (5) numbered single-sided pages
Applies to: person
View source 1
“Subfactor 2: Key Personnel Excluded from Overall Page Limit: Table of Contents, Cover Letter, and Resumes II. 2 Past Performance Maximum Overall Page Limit: Five (5) numbered single-sided pages”
Source page 9
Page markings may include other requirements. The quotation above identifies this requirement.

NOTE: Pages that exceed the required page limitations will not be evaluated. Additional pages
View source 3
“NOTE: Pages that exceed the required page limitations will not be evaluated. Additional pages”
Source page 10
Page markings may include other requirements. The quotation above identifies this requirement.

“NOTE: Pages that exceed the required page limitations will not be evaluated. Additional pages”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

“NOTE: Pages that exceed the required page limitations will not be evaluated. Additional pages”
Source page 23
Page markings may include other requirements. The quotation above identifies this requirement.

Subfactor 2: Key Personnel Excluded from Overall Page Limit: Table of Contents, Cover Letter, and Resumes II. 2 Past Performance Maximum Overall Page Limit: Five (5) numbered single-sided pages III 3 Price No Limit for the price proposal and/or any supporting narrative informatioClose full requirement
Subfactor 2: Key Personnel Excluded from Overall Page Limit: Table of Contents, Cover Letter, and Resumes II. 2 Past Performance Maximum Overall Page Limit: Five (5) numbered single-sided pages III 3 Price No Limit for the price proposal and/or any supporting narrative informatio
Applies to: person
View source 2
“Subfactor 2: Key Personnel Excluded from Overall Page Limit: Table of Contents, Cover Letter, and Resumes II. 2 Past Performance Maximum Overall Page Limit: Five (5) numbered single-sided pages III 3 Price No Limit for the price proposal and/or any supporting narrative information NOTE: Pages that e”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

“Subfactor 2: Key Personnel Excluded from Overall Page Limit: Table of Contents, Cover Letter, and Resumes II. 2 Past Performance Maximum Overall Page Limit: Five (5) numbered single-sided pages III 3 Price No Limit for the price proposal and/or any supporting narrative information”
Source page 22
Page markings may include other requirements. The quotation above identifies this requirement.

Personnel Excluded from Overall Page Limit: Table
View source 1
“Personnel Excluded from Overall Page Limit: Table”
Source page 22
Page markings may include other requirements. The quotation above identifies this requirement.

Volume Factor Title Page Limits
View source 1
“Volume Factor Title Page Limits”
Source page 23
Page markings may include other requirements. The quotation above identifies this requirement.

W90VN827RA0010001 Page 24 of 32 I. 1 Technical Approach, Overall Page Limit: Twenty (20) single-sided Subfactor 1: Prime pages Contractor's Registrations & Resumes: Required for all Key Certifications Personnel.
View source 1
“W90VN827RA0010001 Page 24 of 32 I. 1 Technical Approach, Overall Page Limit: Twenty (20) single-sided Subfactor 1: Prime pages Contractor's Registrations & Resumes: Required for all Key Certifications Personnel.”
Source page 24
Page markings may include other requirements. The quotation above identifies this requirement.

Missing information6 checks · expand to review
A missing value is not a waiver. Check the source or ask the agency before relying on it.
Questions due
2 findings—
Not found in reviewed sources
—
Not reviewed — requirement not confirmed
Site visit / pre-bid meeting
2 findings—
Not found in reviewed sources
—
Not reviewed — requirement not confirmed
Acknowledge amendments
2 findings—
Not found in reviewed sources
—
Not reviewed — requirement not confirmed
6 additional fields have no reviewed finding.
6 more sections are available once you sign in
Pricing & payment · Bonds & insurance · Evaluation & award · Scope & delivery · Labor, sourcing & compliance · Contract terms & risk
Sign in — freeExtracted from the public documents linked above. This is an information aid, not a determination of bid eligibility or legal advice. Verify the original wording and any addenda before submitting a bid.