VETERANS AFFAIRS, DEPARTMENT OF · Wilmington, DE

Z1DA-- 460-26-004 | Wilmington VAMC Roof Replacement | NCO 4 Construction East (VA-26-00029152)

14 source documentsSource checked Oct 21Content updated
Open notice
Response deadline
12 days left
Published project value
Not confirmed
Check the pricing and payment terms below.
Solicitation number
36C24426B0015

Dates to plan around

Times follow the original source.

  1. Response deadline
    Source wording
    2026-11-04T11:00:00-05:00
Document coverage
10 / 14documents readReview incomplete

14 documents found3 partially read1 need OCR5% of weighted requirement checks reviewed

Newer source changes have not been verified. Confirm the latest notice and addenda before submitting.

Before you bid

Review first

Start with these requirements and unresolved points.
01

Eligibility & participation

Whether you can bid at all, and what you must already hold.

1 verified

Set-aside

3 findings
Requirement 1Verified

SDVOSBC

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/badd7126ba3d48de8d8fed64ede193d5 /data2/solicitation/setAsideView official source ↗
“SDVOSBC”
Missing information · 2 checks
Not reviewed

—

Not reviewed — requirement not confirmed

Not found

—

Not found in reviewed sources

Missing information8 checks · expand to review

A missing value is not a waiver. Check the source or ask the agency before relying on it.

Registrations

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

Small business size

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

Required licenses

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

Experience & references

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

6 additional fields have no reviewed finding.

02

Deadlines & submission

When and how to submit, and whether you are still in time.

10 verified

Response deadline

3 findings
Requirement 1Verified

2026-11-04T11:00:00-05:00

View source 2
01https://sam.gov/api/prod/opps/v2/opportunities/badd7126ba3d48de8d8fed64ede193d5 /data2/solicitation/deadlines/responseView official source ↗
“2026-11-04T11:00:00-05:00”
02from the postingView official source ↗
“IFB Bid Opening: November 4th, 2026 11:00AM”
Missing information · 2 checks
Not reviewed

—

Not reviewed — requirement not confirmed

Not found

—

Not found in reviewed sources

Site visit / pre-bid meeting

3 findings
Requirement 1Verified

September 15th, 11:00AM; Meet in building 10 Conference room

View source 1
01from the postingView official source ↗
“Wilmington VAMC Roof Replacement Site Visit: September 15th, 11:00AM; Meet in building 10 Conference room”
Missing information · 2 checks
Not reviewed

—

Not reviewed — requirement not confirmed

Not found

—

Not found in reviewed sources

Procurement contact

Verified

Kevin Rodgers · Kevin.Rodgers2@va.gov

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/badd7126ba3d48de8d8fed64ede193d5 /data2/pointOfContact/0View official source ↗
“Kevin Rodgers · Kevin.Rodgers2@va.gov”

Mandatory forms

5 findings
Requirement 1Verified
Prior RFI Response 27 identified DE20260008; confirm that revision on SAM.gov. 2. SF1442 Block 11 states 30 calendar days, RFI Response 23 states 120 days, and RFI Responses 80 and 104 state 60 days after Notice to Proceed.Read full requirement Close full requirement

Prior RFI Response 27 identified DE20260008; confirm that revision on SAM.gov. 2. SF1442 Block 11 states 30 calendar days, RFI Response 23 states 120 days, and RFI Responses 80 and 104 state 60 days after Notice to Proceed.

View source 1
01para 1; para 2; para 3; para 4; para 5View official source ↗
“Prior RFI Response 27 identified DE20260008; confirm that revision on SAM.gov. 2. SF1442 Block 11 states 30 calendar days, RFI Response 23 states 120 days, and RFI Responses 80 and 104 state 60 days after Notice to Proceed.”
Requirement 2Verified
Please also confirm whether the completion period begins before the VA and AT&T equipment relocations are complete, and how delayed roof access will be addressed. SF1442 Block 11 and FAR 52.211-10 control until amended: start within 10 calendar days of NTP and complete within 30 Read full requirement Close full requirement

Please also confirm whether the completion period begins before the VA and AT&T equipment relocations are complete, and how delayed roof access will be addressed. SF1442 Block 11 and FAR 52.211-10 control until amended: start within 10 calendar days of NTP and complete within 30

Applies when: before the VA and AT&T equipment relocations are complete, and how delayed roof accessMust be met by: before the VA and AT&T equipment relocations are complete, and how delayed roof access

View source 1
01para 1; para 2; para 3; para 4; para 5View official source ↗
“Please also confirm whether the completion period begins before the VA and AT&T equipment relocations are complete, and how delayed roof access will be addressed. SF1442 Block 11 and FAR 52.211-10 control until amended: start within 10 calendar days of NTP and complete within 30 calendar days of NTP”
Requirement 3Verified
A certified SDVOSB subcontractor counts toward limitations on subcontracting but does not count as the prime's own forces. 5. SF1442 indicates that an offer guarantee and performance and payment bonds are not required, but the bid-opening instructions reference submission of bidsRead full requirement Close full requirement

A certified SDVOSB subcontractor counts toward limitations on subcontracting but does not count as the prime's own forces. 5. SF1442 indicates that an offer guarantee and performance and payment bonds are not required, but the bid-opening instructions reference submission of bids

Applies to: subcontractor

View source 1
01para 6; para 7; para 10; para 11; para 12View official source ↗
“A certified SDVOSB subcontractor counts toward limitations on subcontracting but does not count as the prime's own forces. 5. SF1442 indicates that an offer guarantee and performance and payment bonds are not required, but the bid-opening instructions reference submission of bids and bid bonds, and ”
Requirement 4Verified

Given the stated magnitude of construction between $250,000 and $500,000, please confirm whether a bid guarantee, performance bond, and payment bond are required, including amounts or percentages, submission deadlines, and acceptable electronic formats, and correct the SF1442 as

View source 1
01para 6; para 7; para 10; para 11; para 12View official source ↗
“Given the stated magnitude of construction between $250,000 and $500,000, please confirm whether a bid guarantee, performance bond, and payment bond are required, including amounts or percentages, submission deadlines, and acceptable electronic formats, and correct the SF1442 as appropriate.”
Requirement 5Verified
Specifically, please confirm whether the bid submission is limited to the completed and signed SF1442/offer, completed Price/Cost Schedule, applicable signed VAAR 852.219-75 certification, required safety/environmental and EMR documentation, acknowledgment of amendments, and any Read full requirement Close full requirement

Specifically, please confirm whether the bid submission is limited to the completed and signed SF1442/offer, completed Price/Cost Schedule, applicable signed VAAR 852.219-75 certification, required safety/environmental and EMR documentation, acknowledgment of amendments, and any

Applies when: if applicable)

View source 1
01para 43; para 44; para 45; para 46; para 47View official source ↗
“Specifically, please confirm whether the bid submission is limited to the completed and signed SF1442/offer, completed Price/Cost Schedule, applicable signed VAAR 852.219-75 certification, required safety/environmental and EMR documentation, acknowledgment of amendments, and any required bid securit”

Alternate proposals

Verified
Over $35k and less than $150,000 requires a payment bond. 6. Please identify the quantity or allowance for metal-deck replacement to be carried in the base bid and clarify whether the approximately 10% deterioration identified in RFI Response 71 is an estimate only or a required Read full requirement Close full requirement

Over $35k and less than $150,000 requires a payment bond. 6. Please identify the quantity or allowance for metal-deck replacement to be carried in the base bid and clarify whether the approximately 10% deterioration identified in RFI Response 71 is an estimate only or a required

View source 1
01para 6; para 7; para 10; para 11; para 12View official source ↗
“Over $35k and less than $150,000 requires a payment bond. 6. Please identify the quantity or allowance for metal-deck replacement to be carried in the base bid and clarify whether the approximately 10% deterioration identified in RFI Response 71 is an estimate only or a required bid quantity, and wh”

Grounds for rejection

Verified

If bid security is required by the solicitation, it shall also be submitted. Failure to provide the signed VAAR 852.219-75 certification will render the offer ineligible for award.

Applies when: If bid security is required by the solicitation, it shall also be submitted

View source 1
01para 43; para 44; para 45; para 46; para 47View official source ↗
“If bid security is required by the solicitation, it shall also be submitted. Failure to provide the signed VAAR 852.219-75 certification will render the offer ineligible for award.”
Missing information8 checks · expand to review

A missing value is not a waiver. Check the source or ask the agency before relying on it.

Questions due

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

How to submit

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

Required submission files

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

Acknowledge amendments

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

4 additional fields have no reviewed finding.

Continue your review

6 more sections are available once you sign in

Pricing & payment · Bonds & insurance · Evaluation & award · Scope & delivery · Labor, sourcing & compliance · Contract terms & risk

Sign in — free

Extracted from the public documents linked above. This is an information aid, not a determination of bid eligibility or legal advice. Verify the original wording and any addenda before submitting a bid.

Bid review
12 days left
See all 4