VETERANS AFFAIRS, DEPARTMENT OF · Marion, IL

657A5-26-111, Triennial Electrical Testing

1 source documentsSource checked Oct 13Content updated
Open notice
Response deadline
17 days left
Published project value
$500K – $1.0M
As stated in the source documents
Solicitation number
36C25526R0186

Dates to plan around

Times follow the original source.

  1. Response deadline
    Source wording
    2026-11-09T15:00:00-06:00
Document coverage
1 / 1documents readAll discovered documents read

1 document found70% of weighted requirement checks reviewed

Before you bid

Review first

Start with these requirements and unresolved points.
01

Eligibility & participation

Whether you can bid at all, and what you must already hold.

24 verified13 to confirm

Registrations

3 findings
Requirement 1Verified

All contractors and Joint Ventures must be certified in SBAVetCert, and registered in SAM.gov at the time of proposal due date through the time of award to be eligible for award.

Applies when: at the time of proposal due date through the time of award to be eligible for awardMust be met by: at the time of proposal due date through the time of award to be eligible for award

View source 1
01page 1View official source ↗
“All contractors and Joint Ventures must be certified in SBAVetCert, and registered in SAM.gov at the time of proposal due date through the time of award to be eligible for award.”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 2Verified

is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [The Contractor shall enter the name and unique entity identifier of each party to the

View source 1
01page 70View official source ↗
“is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [The Contractor shall enter the name and unique entity identifier of each party to the”
Source page 70

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 70
Missing information · 1 check
Not reviewed

—

Not reviewed — requirement not confirmed

Set-aside

5 findings
Requirement 1Verified

SDVOSBS

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/10b18207f09e44ee91748da26725c0dc /data2/solicitation/setAsideView official source ↗
“SDVOSBS”
Requirement 2Verified

SDVOSB

View source 1
01page 1View official source ↗
“This project is being solicited as a Service-Disabled Veteran Owned Small Business (SDVOSB) set aside.”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 3Verified

SDVOSB,HUBZONE

Applies when: unless the Contractor waived the price evaluation preferenceA waiver may be available

View source 1
01page 69View official source ↗
“(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or (3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dolla”
Source page 69

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 69
Requirement 4Verified

HUBZONE

View source 1
01page 70View official source ↗
“joint venture: _____.] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern.”
Source page 70

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 70
Missing information · 1 check
Not reviewed

—

Not reviewed — requirement not confirmed

Small business size

13 findings
Requirement 1Verified

$19,000,000

View source 1
01page 1View official source ↗
“The NAICS code for this project is 238210- Electrical Contractors and Other Wiring Installation Contractors, the size standard of $19.0 Million.”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 2Needs confirmation

—

Needs confirmation

View source 1
01page 68View official source ↗
“Small business concern— (1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.”
Source page 68

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 68
Requirement 3Needs confirmation

—

Needs confirmation

Applies when: If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified; prior to award of this contract, the ContMust be met by: prior to award of this contract, the Cont

View source 1
01page 68View official source ↗
“SBA determines affiliation based on the factors set forth at 13 CFR 121.103. (b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of thi”
Source page 68

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 68
Requirement 4Needs confirmation

—

Needs confirmation

Applies when: at the time of this rerepresentation that corresponds to the North American Industry ClassificMust be met by: at the time of this rerepresentation that corresponds to the North American Industry Classific

View source 1
01page 69View official source ↗
“(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract.”
Source page 69

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 69
Requirement 5Needs confirmation

—

Needs confirmation

View source 1
01page 69View official source ↗
“The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document/support--table-size-standards.”
Source page 69

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 69
Requirement 6Needs confirmation

—

Needs confirmation

Applies when: if the acquisit

View source 1
01page 69View official source ↗
“(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541”
Source page 69

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 69
Requirement 7Needs confirmation

—

Needs confirmation

View source 1
01page 90View official source ↗
“(iii) The business meets Federal small business size standards for the applicable North American Industry Classification System (NAICS) code identified in the solicitation document;”
Source page 90

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 90
Requirement 8Needs confirmation

—

Needs confirmation

View source 1
01page 90View official source ↗
“In order for a concern to submit an offer and be eligible for the award of an SDVOSB set-aside or sole source contract, the concern must qualify as a small business concern under the size standard corresponding to the NAICS code assigned to the contract and be listed as an SDVOSB participant in the ”
Source page 90

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 90
Requirement 9Needs confirmation

—

Needs confirmation

View source 1
01page 91View official source ↗
“By submitting an offer, the prospective contractor represents that it is an eligible and certified SDVOSB as defined in this clause, 13 CFR 121, 125, and 128, and VAAR subpart 819.70. (d) Agreement/LOS certification.”
Source page 91

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 91
Requirement 10Needs confirmation

—

Needs confirmation

View source 1
01page 91View official source ↗
“business size, and government contracting programs at 13 CFR part 121 and part 125, including the non-manufacturer rule and limitations on subcontracting (LOS) requirements in 13”
Source page 91

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 91
Requirement 11Needs confirmation

—

Needs confirmation

Applies when: unless a waiver as described in 13 CFR 121A waiver may be available

View source 1
01page 91View official source ↗
“(ii) In the case of a contract for supplies from a non-manufacturer, the SDVOSB prime contractor will supply the product of a domestic small business manufacturer or processor, unless a waiver as described in 13 CFR 121.406(b)(5) has been granted.”
Source page 91

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 91
Requirement 12Needs confirmation

—

Needs confirmation

Applies to: subcontractor

View source 1
01page 92View official source ↗
“An SDVOSB subcontractor must meet the NAICS size standard assigned by the prime contractor and be certified and listed in the SBA certification database to count as similarly situated.”
Source page 92

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 92
Missing information · 1 check
Not reviewed

—

Not reviewed — requirement not confirmed

Experience & references

3 findings
Requirement 1Needs confirmation

—

Needs confirmation

View source 1
01page 9View official source ↗
“The Supervising Field Engineer must be accredited as a Certified Electrical Testing Technologist by the National Institute for Certification of Engineering Technologists (NICET) or NETA and have a minimum of 5 years’ experience on similar testing projects of the scope identified in this SOW.”
Source page 9

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 9
Requirement 2Needs confirmation

—

Needs confirmation

Applies when: at least five years of successful experience

Applies to: subcontractor

View source 1
01page 51View official source ↗
“Subcontractor must have technical qualifications of at least five years of successful experience.”
Source page 51

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 51
Missing information · 1 check
Not reviewed

—

Not reviewed — requirement not confirmed

Key personnel

3 findings
Requirement 1Verified

4. Technical Qualifications of Proposed Key Personnel.

Applies to: person

View source 1
01page 48View official source ↗
“4. Technical Qualifications of Proposed Key Personnel.”
Source page 48

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 48
Requirement 2Verified
Such offerors may submit relevant past performance information regarding predecessor companies; key personnel who have relevant experience; or subcontractors that will be performing major or critical aspects of this requirement, provided that such information is relevant to the cRead full requirement Close full requirement

Such offerors may submit relevant past performance information regarding predecessor companies; key personnel who have relevant experience; or subcontractors that will be performing major or critical aspects of this requirement, provided that such information is relevant to the c

Applies when: provided that such information is relevant to the construction in this Page 49 of 138 Page

Applies to: subcontractor

View source 1
01page 49View official source ↗
“Such offerors may submit relevant past performance information regarding predecessor companies; key personnel who have relevant experience; or subcontractors that will be performing major or critical aspects of this requirement, provided that such information is relevant to the construction in this ”
Source page 49

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 49
Requirement 3Verified
Note that offers that are not technically acceptable cannot be selected, regardless of price. 4. SPECIAL CONTRACT REQUIREMENTS SUBSTITUTIONS OF SUBCONTRACTORS AND / OR KEY PERSONNEL 1. When an offeror submits its proposal in response to this Request for Proposals, and key personnRead full requirement Close full requirement

Note that offers that are not technically acceptable cannot be selected, regardless of price. 4. SPECIAL CONTRACT REQUIREMENTS SUBSTITUTIONS OF SUBCONTRACTORS AND / OR KEY PERSONNEL 1. When an offeror submits its proposal in response to this Request for Proposals, and key personn

Applies when: When an offeror submits its proposal in response to this Request for Proposals, and key personnel who are proposed to work on the proje

Applies to: subcontractor

View source 1
01page 54View official source ↗
“Note that offers that are not technically acceptable cannot be selected, regardless of price. 4. SPECIAL CONTRACT REQUIREMENTS SUBSTITUTIONS OF SUBCONTRACTORS AND / OR KEY PERSONNEL 1. When an offeror submits its proposal in response to this Request for Proposals, and key personnel who are proposed ”
Source page 54

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 54

Financial capacity

Verified

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury D

Applies to: surety

View source 1
01page 59View official source ↗
“(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulation”
Source page 59

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 59

Joint ventures & teaming

12 findings
Requirement 1Verified

All contractors and Joint Ventures must be certified in SBAVetCert, and registered in SAM.gov at the time of proposal due date through the time of award to be eligible for award.

Applies when: at the time of proposal due date through the time of award to be eligible for awardMust be met by: at the time of proposal due date through the time of award to be eligible for award

View source 1
01page 1View official source ↗
“All contractors and Joint Ventures must be certified in SBAVetCert, and registered in SAM.gov at the time of proposal due date through the time of award to be eligible for award.”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 2Verified

Contractor employee means an employee of the prime contractor or of any subcontractor, affiliate, partner, joint venture, or team members with which the contractor is associated.

Applies to: subcontractor

View source 1
01page 27View official source ↗
“Contractor employee means an employee of the prime contractor or of any subcontractor, affiliate, partner, joint venture, or team members with which the contractor is associated.”
Source page 27

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 27
Requirement 3Verified

Note: Proposals submitted by teaming arrangements other than VA SDVOSB Joint Ventures will

View source 1
01page 47View official source ↗
“Note: Proposals submitted by teaming arrangements other than VA SDVOSB Joint Ventures will”
Source page 47

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 47
Requirement 4Verified

If Submitting as a Joint Venture, you are required to submit a copy of the Joint Venture agreement with proposal. c.

Applies when: If Submitting as a Joint Venture, you are required to submit a copy of the Joint Venture agreement with proposal

View source 1
01page 47View official source ↗
“If Submitting as a Joint Venture, you are required to submit a copy of the Joint Venture agreement with proposal. c.”
Source page 47

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 47
Requirement 5Verified

Offerors who fail to submit experience for all Joint Venture partners will receive no further consideration.

View source 1
01page 51View official source ↗
“Offerors who fail to submit experience for all Joint Venture partners will receive no further consideration.”
Source page 51

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 51
Requirement 6Verified

If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity.

Applies when: If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity

View source 1
01page 51View official source ↗
“If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity.”
Source page 51

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 51
Requirement 7Verified

If the Joint Venture does not have shared experience, projects shall be submitted for each Joint Venture partner.

Applies when: If the Joint Venture does not have shared experience, projects shall be submitted for each Joint Venture partner

View source 1
01page 51View official source ↗
“If the Joint Venture does not have shared experience, projects shall be submitted for each Joint Venture partner.”
Source page 51

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 51
Requirement 8Verified
SBA determines affiliation based on the factors set forth at 13 CFR 121.103. (b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) pRead full requirement Close full requirement

SBA determines affiliation based on the factors set forth at 13 CFR 121.103. (b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) p

Applies when: If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified; prior to award of this contract, the ContMust be met by: prior to award of this contract, the Cont

View source 1
01page 68View official source ↗
“SBA determines affiliation based on the factors set forth at 13 CFR 121.103. (b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of thi”
Source page 68

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 68
Requirement 9Verified

(4) Economically disadvantaged women-owned small business (EDWOSB) joint venture.

View source 1
01page 70View official source ↗
“(4) Economically disadvantaged women-owned small business (EDWOSB) joint venture.”
Source page 70

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 70
Requirement 10Verified

(f) Joint ventures.

View source 1
01page 92View official source ↗
“(f) Joint ventures.”
Source page 92

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 92
Requirement 11Verified

A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (d) of this clause will be performed by the aggregate of the joint venture participants.

View source 1
01page 92View official source ↗
“A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (d) of this clause will be performed by the aggregate of the joint venture participants.”
Source page 92

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 92
Requirement 12Verified
A joint venture may be considered eligible as an SDVOSB if the joint venture complies with the requirements in 13 CFR 128.402 and the managing joint venture partner makes the representations under paragraph (c) of this clause.Read full requirement Close full requirement

A joint venture may be considered eligible as an SDVOSB if the joint venture complies with the requirements in 13 CFR 128.402 and the managing joint venture partner makes the representations under paragraph (c) of this clause.

Applies when: if the joint venture complies with the requirements in 13 CFR 128

View source 1
01page 92View official source ↗
“A joint venture may be considered eligible as an SDVOSB if the joint venture complies with the requirements in 13 CFR 128.402 and the managing joint venture partner makes the representations under paragraph (c) of this clause.”
Source page 92

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 92

Exclusions & responsibility

Verified
(e) In the event that the Contractor does not comply with the requirements set forth in paragraphs (a) through (d) of this clause, this contract may be terminated or suspended in whole or in part, and the Contractor may be suspended or debarred in accordance with 29 CFR 471.14 anRead full requirement Close full requirement

(e) In the event that the Contractor does not comply with the requirements set forth in paragraphs (a) through (d) of this clause, this contract may be terminated or suspended in whole or in part, and the Contractor may be suspended or debarred in accordance with 29 CFR 471.14 an

View source 1
01page 71View official source ↗
“(e) In the event that the Contractor does not comply with the requirements set forth in paragraphs (a) through (d) of this clause, this contract may be terminated or suspended in whole or in part, and the Contractor may be suspended or debarred in accordance with 29 CFR 471.14 and subpart 9.4. Such ”
Source page 71

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 71
Missing information2 checks · expand to review

A missing value is not a waiver. Check the source or ask the agency before relying on it.

Required licenses

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

2 additional fields have no reviewed finding.

02

Deadlines & submission

When and how to submit, and whether you are still in time.

10 verified4 to confirm

Response deadline

3 findings
Requirement 1Verified

2026-11-09T15:00:00-06:00

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/10b18207f09e44ee91748da26725c0dc /data2/solicitation/deadlines/responseView official source ↗
“2026-11-09T15:00:00-06:00”
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

How to submit

4 findings
Requirement 1Verified

CONTRACTORS WILL BE REQUIRED TO ELECTRONICALLY SUBMIT PROPOSAL BY EMAIL TO MARIA HOOVER and KEVIN MAHONEY. email: maria.hoover@va.gov, phone 913-946-1127 and kevin.mahoney3@va.gov phone 913-684-0141. (CONTRACTOR WILL BE REQUIRED TO VERIFY THAT THE EMAIL HAS BEEN RECEIVED WITH ATT

View source 1
01page 1View official source ↗
“CONTRACTORS WILL BE REQUIRED TO ELECTRONICALLY SUBMIT PROPOSAL BY EMAIL TO MARIA HOOVER and KEVIN MAHONEY. email: maria.hoover@va.gov, phone 913-946-1127 and kevin.mahoney3@va.gov phone 913-684-0141. (CONTRACTOR WILL BE REQUIRED TO VERIFY THAT THE EMAIL HAS BEEN RECEIVED WITH ATTACHED PROPOSAL DOCUM”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 2Verified

Bid Bond shall be included in emailed proposal and hard copy mailed to address in block 8 by proposal closing date.

View source 1
01page 1View official source ↗
“Bid Bond shall be included in emailed proposal and hard copy mailed to address in block 8 by proposal closing date.”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 3Verified

(3) Proposals shall be submitted to the Contracting Officer or ACO and the resident engineer as expeditiously as possible, but not later than calendar days, after receipt of a written change order by the Contracting Officer.

View source 1
01page 97View official source ↗
“(3) Proposals shall be submitted to the Contracting Officer or ACO and the resident engineer as expeditiously as possible, but not later than calendar days, after receipt of a written change order by the Contracting Officer.”
Source page 97

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 97
Missing information · 1 check
Not reviewed

—

Not reviewed — requirement not confirmed

Required submission files

2 findings
Requirement 1Verified

Offerors shall e-mail three files to maria.hoover@va.gov and kevin.mahoney3@va.gov and the package shall include: Volume 1 Technical Proposal and 852.219-75 VA Notice of Limitations on Subcontracting .

View source 1
01page 47View official source ↗
“Offerors shall e-mail three files to maria.hoover@va.gov and kevin.mahoney3@va.gov and the package shall include: Volume 1 Technical Proposal and 852.219-75 VA Notice of Limitations on Subcontracting .”
Source page 47

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 47
Missing information · 1 check
Not reviewed

—

Not reviewed — requirement not confirmed

Acknowledge amendments

2 findings
Requirement 1Verified

NOTE: Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of your offer. b.

View source 1
01page 48View official source ↗
“NOTE: Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of your offer. b.”
Source page 48

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 48
Missing information · 1 check
Not reviewed

—

Not reviewed — requirement not confirmed

Procurement contact

2 findings
Requirement 1Verified

Kevin A Mahoney · Kevin.Mahoney3@va.gov · 9136840141

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/10b18207f09e44ee91748da26725c0dc /data2/pointOfContact/0View official source ↗
“Kevin A Mahoney · Kevin.Mahoney3@va.gov · 9136840141”
Requirement 2Needs confirmation

—

Needs confirmation

View source 1
01page 11View official source ↗
“and approved by the Contracting Officer:”
Source page 11

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 11

Bid opening

3 findings
Requirement 1Needs confirmation

—

Needs confirmation

Applies when: If this is a sealed bid solicitation, offers must be publicly opened at that time

View source 1
01page 1View official source ↗
“If this is a sealed bid solicitation, offers must be publicly opened at that time.”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 2Needs confirmation

—

Needs confirmation

View source 1
01page 59View official source ↗
“(End of Provision) 2.4 52.228-1 BID GUARANTEE (SEP 1996) (a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.”
Source page 59

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 59
Requirement 3Needs confirmation

—

Needs confirmation

Applies when: upon execution of contractual documents and bonds (including any necessary coinsuranMust be met by: upon execution of contractual documents and bonds (including any necessary coinsuran

View source 1
01page 59View official source ↗
“The Contracting Officer will return bid guarantees, other than bid bonds— (1) To unsuccessful bidders as soon as practicable after the opening of bids; and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), ”
Source page 59

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 59

Grounds for rejection

3 findings
Requirement 1Verified

NOTE: Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of your offer. b.

View source 1
01page 48View official source ↗
“NOTE: Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of your offer. b.”
Source page 48

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 48
Requirement 2Verified
In accordance with solicitation provision 52.228-1, Bid Guarantee, failure to furnish a bid guarantee, in the proper form and amount, by the deadline established for submitting offers, will be cause for rejection of the offer. c.Read full requirement Close full requirement

In accordance with solicitation provision 52.228-1, Bid Guarantee, failure to furnish a bid guarantee, in the proper form and amount, by the deadline established for submitting offers, will be cause for rejection of the offer. c.

View source 1
01page 48View official source ↗
“In accordance with solicitation provision 52.228-1, Bid Guarantee, failure to furnish a bid guarantee, in the proper form and amount, by the deadline established for submitting offers, will be cause for rejection of the offer. c.”
Source page 48

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 48
Requirement 3Verified

(End of Provision) 2.4 52.228-1 BID GUARANTEE (SEP 1996) (a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

View source 1
01page 59View official source ↗
“(End of Provision) 2.4 52.228-1 BID GUARANTEE (SEP 1996) (a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.”
Source page 59

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 59
Missing information4 checks · expand to review

A missing value is not a waiver. Check the source or ask the agency before relying on it.

Questions due

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

Site visit / pre-bid meeting

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

5 additional fields have no reviewed finding.

Continue your review

6 more sections are available once you sign in

Pricing & payment · Bonds & insurance · Evaluation & award · Scope & delivery · Labor, sourcing & compliance · Contract terms & risk

Sign in — free

Extracted from the public documents linked above. This is an information aid, not a determination of bid eligibility or legal advice. Verify the original wording and any addenda before submitting a bid.

$500K – $1.0M
17 days left
See all 13