BidEligible

AGRICULTURE, DEPARTMENT OF · Garden City, UT

GAOA Tony Grove Dam Spillway Capacity & Seismic Mitigation, Uinta/Wasatch/Cache National Forest

6 source documentsSource checked Oct 22Content updated
Open notice
Response deadline
28 days left
Published project value
Not confirmed
Check the pricing and payment terms below.
Solicitation number
1240BH27Q0002
View official posting ↗Review requirements ↓Original posting details are available below.

Dates to plan around

Times follow the original source.

  1. Response deadline
    Source wording
    2026-11-20T17:00:00-07:00
From the posting2 agency details · contact information and original wording
Solicitation number
Solicitation number 1240BH27Q0002
Worth confirming on the posting
Scope
Extend quote due date to November 20, 2026.
View the official posting →Always the authority. An addendum can change any of this after we read it.
Document coverage
6 / 6documents readAll discovered documents read

6 documents found62% of weighted requirement checks reviewed

Before you bid

Review first

Start with these requirements and unresolved points.
  • Must do
    Registrations
    View 1 flagged requirement
    1. Requirement 1 ↗

      All Contractors must be registered in the System for Award Management (www.SAM.gov) at time of submission of a quote.

  • Must do
01

Eligibility & participation

Whether you can bid at all, and what you must already hold.

10 verified2 to confirm

Registrations

3 findings
Requirement 1Verified

All Contractors must be registered in the System for Award Management (www.SAM.gov) at time of submission of a quote.

View source 1
01page 1View official source ↗
“All Contractors must be registered in the System for Award Management (www.SAM.gov) at time of submission of a quote.”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Missing information · 2 checks
Not reviewed

—

Not reviewed — requirement not confirmed

Not found

—

Not found in reviewed sources

Set-aside

3 findings
Requirement 1Verified

SBA

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/dc614806cdda4cf7a65ba7034b459649 /data2/solicitation/setAsideView official source ↗
“SBA”
Missing information · 2 checks
Not reviewed

—

Not reviewed — requirement not confirmed

Not found

—

Not found in reviewed sources

Small business size

3 findings
Requirement 1Verified

$45,000,000

View source 2
01page 1View official source ↗
“- NAICS: 237990 with a Small Business Size Standard of $45 Million. This acquisition”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
02notice bodyView official source ↗
“The small business size standard is $45 Million.”
Missing information · 2 checks
Not reviewed

—

Not reviewed — requirement not confirmed

Not found

—

Not found in reviewed sources

Experience & references

4 findings
Requirement 1Needs confirmation

—

Needs confirmation

View source 1
01page 16View official source ↗
“The crew chief shall have a minimum of 5 years of experience in responsible charge of construction surveys for construction similar in nature to that required for this contract.”
Source page 16

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 16
Requirement 2Needs confirmation

—

Needs confirmation

Applies when: at least five years

View source 1
01page 91View official source ↗
“The manufacturer shall have manufactured tight-closing, rubber-seat butterfly valves for a period of at least five years.”
Source page 91

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 91
Missing information · 2 checks
Not reviewed

—

Not reviewed — requirement not confirmed

Not found

—

Not found in reviewed sources

Key personnel

4 findings
Requirement 1Verified

The work shall also include participation of Contractor’s key personnel in weekly coordination meetings with the Engineer.

Applies to: person

View source 1
01page 18View official source ↗
“The work shall also include participation of Contractor’s key personnel in weekly coordination meetings with the Engineer.”
Source page 18

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 18
Requirement 2Verified
(ii) Subfactor 2 – Project Management and Oversight: The Government will assess and evaluate the overall organizational structure and resumes for key personnel as submitted with focus on experience and expertise in the types of work required under the scope of work for this projeRead full requirement Close full requirement

(ii) Subfactor 2 – Project Management and Oversight: The Government will assess and evaluate the overall organizational structure and resumes for key personnel as submitted with focus on experience and expertise in the types of work required under the scope of work for this proje

Applies to: person

View source 1
01page 19View official source ↗
“(ii) Subfactor 2 – Project Management and Oversight: The Government will assess and evaluate the overall organizational structure and resumes for key personnel as submitted with focus on experience and expertise in the types of work required under the scope of work for this project.”
Source page 19

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 19
Requirement 3Verified
Where there is little or no information available regarding the firm’s past performance history because the firm is new to the marketplace, the past performance evaluation may take into account information regarding predecessor companies, key personnel who have relevant experiencRead full requirement Close full requirement

Where there is little or no information available regarding the firm’s past performance history because the firm is new to the marketplace, the past performance evaluation may take into account information regarding predecessor companies, key personnel who have relevant experienc

Applies to: subcontractor

View source 1
01page 20View official source ↗
“Where there is little or no information available regarding the firm’s past performance history because the firm is new to the marketplace, the past performance evaluation may take into account information regarding predecessor companies, key personnel who have relevant experience, or subcontractors”
Source page 20

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 20
Requirement 4Verified

Additionally, provide resumes for staff members for each of the following key positions.

View source 1
01page 22View official source ↗
“Additionally, provide resumes for staff members for each of the following key positions.”
Source page 22

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 22

Financial capacity

2 findings
Requirement 1Verified

☐ 52.228-13 Alternative Payment Protections (Jul 2020) ☒ 52.228-14 Irrevocable Letter of Credit (Nov 2014)

View source 1
01page 11View official source ↗
“☐ 52.228-13 Alternative Payment Protections (Jul 2020) ☒ 52.228-14 Irrevocable Letter of Credit (Nov 2014)”
Source page 11

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 11
Requirement 2Verified

GAOA Tony Grove Dam Spillway Capacity & Seismic Mitigation RFQ 1240BH27Q0002 (b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certifi

Applies to: surety

View source 1
01page 25View official source ↗
“GAOA Tony Grove Dam Spillway Capacity & Seismic Mitigation RFQ 1240BH27Q0002 (b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's ”
Source page 25

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 25

Exclusions & responsibility

Verified

☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025)

Applies when: When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025)

View source 1
01page 9View official source ↗
“☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025)”
Source page 9

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 9
Missing information2 checks · expand to review

A missing value is not a waiver. Check the source or ask the agency before relying on it.

Required licenses

2 findings
Requirement 1Not reviewed

—

Not reviewed — requirement not confirmed

Requirement 2Not found

—

Not found in reviewed sources

3 additional fields have no reviewed finding.

02

Deadlines & submission

When and how to submit, and whether you are still in time.

17 verified3 to confirm

Response deadline

3 findings
Requirement 1Verified

2026-11-20T17:00:00-07:00

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/dc614806cdda4cf7a65ba7034b459649 /data2/solicitation/deadlines/responseView official source ↗
“2026-11-20T17:00:00-07:00”
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

How to submit

4 findings
Requirement 1Verified

USDA-FS CSA NORTHWEST 6 Judith Martin 1220 SW 3RD AVE Email quotes to PPS.proposals@usda.gov

View source 1
01page 1View official source ↗
“USDA-FS CSA NORTHWEST 6 Judith Martin 1220 SW 3RD AVE Email quotes to PPS.proposals@usda.gov”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 2Verified

Contractors shall submit a quote for all Items in the Schedule of Items.

View source 1
01page 23View official source ↗
“Contractors shall submit a quote for all Items in the Schedule of Items.”
Source page 23

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 23
Missing information · 2 checks
Not found

—

Not found in reviewed sources

Not reviewed

—

Not reviewed — requirement not confirmed

Procurement contact

3 findings
Requirement 1Verified

Judith Martin · judith.martin@usda.gov

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/dc614806cdda4cf7a65ba7034b459649 /data2/pointOfContact/0View official source ↗
“Judith Martin · judith.martin@usda.gov”
Requirement 2Verified

Janet Paul · janet.paul@usda.gov · 541-750-7120

View source 1
01https://sam.gov/api/prod/opps/v2/opportunities/dc614806cdda4cf7a65ba7034b459649 /data2/pointOfContact/1View official source ↗
“Janet Paul · janet.paul@usda.gov · 541-750-7120”
Requirement 3Needs confirmation

—

Needs confirmation

View source 1
01page 23View official source ↗
“GAOA Tony Grove Dam Spillway Capacity & Seismic Mitigation RFQ 1240BH27Q0002 (6) Point of Contact (POC) name/phone/email of project owner representative.”
Source page 23

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 23

Bid opening

2 findings
Requirement 1Needs confirmation

—

Needs confirmation

Applies when: If this is a sealed bid solicitation, offers will be publicly opened at that time

View source 1
01page 1View official source ↗
“If this is a sealed bid solicitation, offers will be publicly opened at that time.”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 2Needs confirmation

—

Needs confirmation

Applies when: upon execution of contractual documents and bonds (including any necessary coinsuranMust be met by: upon execution of contractual documents and bonds (including any necessary coinsuran

View source 1
01page 25View official source ↗
“The Contracting Officer will return bid guarantees, other than bid bonds – (1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements),”
Source page 25

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 25

Mandatory forms

5 findings
Requirement 1Verified

Unita/Wasatch/Cache National Forest, is amended as follows: See Attachment 1 Solicitation, Pg 1, SF-1442, 13. ADDITIONAL SOLICITATION REQUIREMENTS,

View source 1
01page 1View official source ↗
“Unita/Wasatch/Cache National Forest, is amended as follows: See Attachment 1 Solicitation, Pg 1, SF-1442, 13. ADDITIONAL SOLICITATION REQUIREMENTS,”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 2Verified

SF-24 shall be used for Bid Bonds - https://www.gsa.gov/reference/forms/bid-bond

View source 1
01page 1View official source ↗
“SF-24 shall be used for Bid Bonds - https://www.gsa.gov/reference/forms/bid-bond”
Source page 1

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 1
Requirement 3Verified

Documents are to be emailed to the Contract Specialist Judith Martin at PPS.proposals@usda.gov no later than the date and time specified on the SF-1442 or any Amendment that extends the time and date.

Applies when: no later than the date and time specified on the SF-1442 or any Amendment that extends the tiMust be met by: no later than the date and time specified on the SF-1442 or any Amendment that extends the ti

View source 1
01page 21View official source ↗
“Documents are to be emailed to the Contract Specialist Judith Martin at PPS.proposals@usda.gov no later than the date and time specified on the SF-1442 or any Amendment that extends the time and date.”
Source page 21

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 21
Requirement 4Verified
This can be accomplished by completing section 19 on the SF-1442 or by submitting the signed SF-30(s) from SAM.gov with your price proposal. 4) Scanned copy of fully executed Bid Guarantee (Standard Form 24 and Power of Attorney).Read full requirement Close full requirement

This can be accomplished by completing section 19 on the SF-1442 or by submitting the signed SF-30(s) from SAM.gov with your price proposal. 4) Scanned copy of fully executed Bid Guarantee (Standard Form 24 and Power of Attorney).

View source 1
01page 23View official source ↗
“This can be accomplished by completing section 19 on the SF-1442 or by submitting the signed SF-30(s) from SAM.gov with your price proposal. 4) Scanned copy of fully executed Bid Guarantee (Standard Form 24 and Power of Attorney).”
Source page 23

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 23
Requirement 5Verified

The SF-24 shall be used for Bid Bonds - https://www.gsa.gov/reference/forms/bid-bond

View source 1
01page 23View official source ↗
“The SF-24 shall be used for Bid Bonds - https://www.gsa.gov/reference/forms/bid-bond”
Source page 23

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 23

Alternate proposals

5 findings
Requirement 1Verified

12'-0" 10' WIDE 3" THICK ASPHALT 10' WIDE (ALTERNATE BID ITEM) 3" THICK ASPHALT 6'-0"

View source 1
01page 16View official source ↗
“12'-0" 10' WIDE 3" THICK ASPHALT 10' WIDE (ALTERNATE BID ITEM) 3" THICK ASPHALT 6'-0"”
Source page 16

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 16
Requirement 2Verified

10' WIDE 3" THICK ASPHALT 10' WIDE (ALTERNATE BID ITEM) 3" THICK ASPHALT 6'-0" (ALTERNATE BID ITEM) -2.0%

View source 1
01page 16View official source ↗
“10' WIDE 3" THICK ASPHALT 10' WIDE (ALTERNATE BID ITEM) 3" THICK ASPHALT 6'-0" (ALTERNATE BID ITEM) -2.0%”
Source page 16

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 16
Requirement 3Verified

10' WIDE 3" THICK ASPHALT (ALTERNATE BID ITEM)

View source 1
01page 16View official source ↗
“10' WIDE 3" THICK ASPHALT (ALTERNATE BID ITEM)”
Source page 16

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 16
Requirement 4Verified
HORROCKS STA E T L E ECSET O AR F LON U IC TAH 03/26/2026 S301 21 ERUTCURTS TSIOH ETAG OIL FILL PIPE WITH LOCKABLE CAP (FILL WITH BIODEGRADABLE OIL) 6 - #4 BARS AS SHOWN ASPHALT (ALTERNATE BID ITEM) LOCKABLE ROADBASE GEARED OPERATOR GATE STEM -1% SLOPE #4 @8" EACH WAY 4" PVC SLEERead full requirement Close full requirement

HORROCKS STA E T L E ECSET O AR F LON U IC TAH 03/26/2026 S301 21 ERUTCURTS TSIOH ETAG OIL FILL PIPE WITH LOCKABLE CAP (FILL WITH BIODEGRADABLE OIL) 6 - #4 BARS AS SHOWN ASPHALT (ALTERNATE BID ITEM) LOCKABLE ROADBASE GEARED OPERATOR GATE STEM -1% SLOPE #4 @8" EACH WAY 4" PVC SLEE

View source 1
01page 21View official source ↗
“HORROCKS STA E T L E ECSET O AR F LON U IC TAH 03/26/2026 S301 21 ERUTCURTS TSIOH ETAG OIL FILL PIPE WITH LOCKABLE CAP (FILL WITH BIODEGRADABLE OIL) 6 - #4 BARS AS SHOWN ASPHALT (ALTERNATE BID ITEM) LOCKABLE ROADBASE GEARED OPERATOR GATE STEM -1% SLOPE #4 @8" EACH WAY 4" PVC SLEEVE FOR STEM #4 @8" E”
Source page 21

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 21
Requirement 5Verified

5. Items of Work and Construction Details Items of work to be performed in accordance with the specifications and the construction details are: Alternate Bid Item – Hot Mix Asphalt The work shall consist of furnishing, placing and compacting the hot mix asphalt materials shown on

View source 1
01page 133View official source ↗
“5. Items of Work and Construction Details Items of work to be performed in accordance with the specifications and the construction details are: Alternate Bid Item – Hot Mix Asphalt The work shall consist of furnishing, placing and compacting the hot mix asphalt materials shown on the Construction Dr”
Source page 133

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 133

Grounds for rejection

2 findings
Requirement 1Verified

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

View source 1
01page 24View official source ↗
“(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.”
Source page 24

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 24
Requirement 2Verified

Cracks in concrete components caused by Contractor fabrication, shrinkage during curing, handling, shipping, and installation shall be cause for rejection UT – Tony Grove Reservoir Outlet, March 2026 487

View source 1
01page 125View official source ↗
“Cracks in concrete components caused by Contractor fabrication, shrinkage during curing, handling, shipping, and installation shall be cause for rejection UT – Tony Grove Reservoir Outlet, March 2026 487”
Source page 125

Page markings may include other requirements. The quotation above identifies this requirement.

Source document page 125
Missing information8 checks · expand to review

A missing value is not a waiver. Check the source or ask the agency before relying on it.

Questions due

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

Site visit / pre-bid meeting

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

Required submission files

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

Acknowledge amendments

2 findings
Requirement 1Not found

—

Not found in reviewed sources

Requirement 2Not reviewed

—

Not reviewed — requirement not confirmed

3 additional fields have no reviewed finding.

Continue your review

6 more sections are available once you sign in

Pricing & payment · Bonds & insurance · Evaluation & award · Scope & delivery · Labor, sourcing & compliance · Contract terms & risk

Sign in — free

Extracted from the public documents linked above. This is an information aid, not a determination of bid eligibility or legal advice. Verify the original wording and any addenda before submitting a bid.

Bid review
28 days left
See all 12